23.43 kW PV · 2 × SPI-12K-UPRO · 48 kWh LiFePO4 · drawn to scale, dimensions in mm
1 · The ceiling. Stacking the inverters above the battery cabinets needs more height than a standard 8-foot room has. The cabinets roll on their own casters, so there is no plinth — that bought back 100 mm. Bottom up:
If the wash room is 8′-0″, the inverters cannot go above the batteries. They go beside them instead, which needs about 4 m of wall — so the plant moves to two walls in an L, batteries on one and inverters on the other. Everything else here stays true; only the arrangement changes. Measure it, then the drawing gets redone.
Worth knowing about that 300 mm: the UPRO manual gives no clearance figures at all. §3.1 asks for “sufficient heat dissipation space” and nothing more. The 300 / 150 / 500 numbers on this drawing are trade practice carried over from the SEI manual, which is a different machine. They are sensible. They are not quoted.
2 · The nine-panel string. The UPRO ceiling is 500 V, not 550. Nine panels at 49 V open-circuit is about 455 V and fine; at 52 V it is 482 V and tight; at 54 V it is over 500 V and the string cannot be used. The panel Voc is still unconfirmed and it is the one number that can force a restring.
Elevation · looking at the wall · services enter top left, return wall at the right · grey channels are conduit and trunking, coloured lines are the circuits inside them
Only SPI-12K-UPRO Manual (Sunpal, 23 Oct 2026) applies.
The SEI-UP, HESP48120U200-H and HEBP-Pro documents in 05-datasheets/ describe a
different machine and were the source of the figures corrected on this revision.
Plan · looking down · the working space is as much a part of the design as the wall is. The inverter is now 150 mm deep rather than 240, so the battery cabinets govern the room depth on their own.
| Ref | Carries | Size | Run | Why separate |
|---|---|---|---|---|
| T1 | Battery 3/0 · 85 mm² — combiner to both inverters | 100 × 75 trunking | 800 mm, local | 520 A. Short, heavy, and nothing else should share its bends. |
| T2 | Battery 2/0 — three cabinets to combiner, plus the three cabinet earths | 100 × 75 trunking | 1,290 mm | Same system as T1 but three times the cable count. The earths ride with their own circuit. |
| T3 | PV DC, four strings at up to 500 V each | 1¼″ conduit | 2,020 mm | High-voltage DC does not share a raceway with 51 V DC or 240 V AC. Different voltage class, different enclosure. |
| T4 | AC — grid in and load out, 240 V | 100 × 75 trunking | 1,830 mm | Grid and load may share; both are 240 V AC. Label the two bundles at every opening. |
| T5 | Battery BMS CAN, inverter parallel link | ¾″ conduit | 1,280 mm | Furthest from the 3/0. A CAN bus run alongside 520 A of switching DC is a fault you will spend a week finding. |
| T6 | Everything to and from the house main panel: JPS feed in, transfer-switch utility source, house feed out, earth bond | 100 × 75 trunking, vertical | 1,160 mm | The only channel that leaves this wall. Four circuits, one route, one set of saddles. |
Ten things this drawing cannot answer on its own. Some block purchases that are otherwise ready to order; the rest decide how something gets installed rather than whether it can be bought. Question 0 comes before all of them — it is the only one that can change the shape of the system rather than the contents of a box.
| # | Ask | What it decides |
|---|---|---|
| 0 | Where exactly do the solar feeds tap into the service, and what does the transfer switch load actually feed? | Ask this first; it can change the shape of the system. This drawing shows two feeds leaving the house main panel (the grid cabinet feed and Source 2) and one arriving at it (the switch load). The panel cannot be upstream and downstream on one busbar: if all three share a bus, then with the switch on SOLAR the inverter output returns through the feed breaker into the inverter's own AC input — it would see “grid present” from itself and never go to battery. The panel is off this wall, through T6, so its internals were never resolved here. Two ways out. (A) A new service disconnect ahead of the panel: meter → disconnect → splits to the grid cabinet feed and Source 2; switch load → existing panel, which becomes 100% backed up. Right for a new build, and the feed breaker then lives in that new disconnect, so its brand stops depending on question 1. (B) A new backed-up sub-panel holding only chosen circuits, with the main panel left on raw utility — cheaper, but solar then covers part of the house and the circuits must be picked now. |
| 1 | What brand and model is the house main panel, and how many spare spaces does it have? | Blocks three purchases. The 100 A feed breaker (if question 0 leaves it in this panel), the AC surge arrester, and the 2-pole breaker a wired-in arrester would need. A Siemens breaker does not fit a Square D panel and plug-in arresters are brand-specific, so there is no brand-agnostic way around this. The feed breaker needs 2 spaces and a plug-in arrester usually wants 2 more. |
| 2 | What size should the earth bus conductor be? | No document in this project gives a figure. Eleven 6 mm² tees hang off one conductor running along the top of this wall — SPD box, transfer switch, both cabinet ground bars, both inverter grounding screws, the combiner body. It has to be at least as big as the largest of them and is almost certainly bigger. A real gap, not a drawing simplification. |
| 3 | Feed breaker — confirm 100 A (and that it is not 70 A) | §4.2 specifies 3P-63 A per inverter. Two inverters is 126 A against a 125 A busbar — one amp over, so the grid cabinet sits at its ceiling by design. The feed breaker protects that bus, so it cannot be sized to the 70 A branches. Mains charge current (item 28, default 60 A, max 120 A — not item 07, which is total battery charge current) can be turned down to buy margin. |
| 4 | 6 AWG or 4 AWG for the two inverter AC branch runs? | 6 AWG is a 65 A conductor. 63 A continuous × 1.25 = 79 A. The runs are about 15 m each and the cable is not yet bought, so this is still free to change. Ask before the cable order goes in, not after. |
| 5 | Are local earth rods at the plant worth it here? | The 4 AWG bond to the house main panel is required and is not in question. A rod is supplementary. A conductor rises roughly 1 kV per metre per kA/µs, so 6 m back to the service earth puts this earth bar tens of kV above it mid-strike. Never a rod without the bond — that version is worse than no rod at all. Two spare positions are left on the earth bar for this. |
| 6 | Is the plant room wall solid/filled concrete or hollow block? | Picks the masonry anchor for everything on this wall. Sleeve and wedge anchors need something to expand against; in a hollow web they feel tight and pull out under load. One test hole settles it — if the bit punches into a void after about 30 mm it is hollow, and the heavy enclosures need toggles or a chemical anchor with screen tubes instead. |
| 7 | Will the inspector want the backfed breaker retainer, and does ECMBR2 satisfy it? |
NEC 408.36(D) requires a plug-in backfed device to be secured by a fastener needing more than a pull to
release. Two genuine Siemens ECMBR2 are bought for the two backfed Q270.
One thing to verify: that kit lists Ultimate / ES / PL load centres and ours is the EQ series
E0816ML1125S. The panel's own installation sheet names the right part. |
| 8 | Does the mounting system provide listed bonding, or do the modules need jumpers? | Decides whether 40 × 4 mm² bonding jumpers and 80 M5 ring terminals get bought at all. Look for toothed grounding mid-clamps, WEEB washers, or a UL 2703 marking on the rail. If the system is listed for bonding, the frames bond through the rail and none of that hardware is needed. |
| 9 | Do we need a DC isolator at the array, on top of the four C25 breakers already in the SPD box? | Decides a purchase that is currently unordered. The four DZ47Z-63 C25 breakers in the
SPD box are 1000 V DC rated, one per string, and lock off — that is already a disconnecting means, indoors
and accessible. An array-side isolator adds one thing the breakers cannot do: it makes the cast-in chase
dead. Open the C25s and the roof-to-wall conductors stay live whenever the sun is up, because a panel has
no off switch. Against it: an enclosure on a roof in a hurricane zone, C4 salt air and full UV is a new failure
point and new penetrations. If yes, it is 8 poles — four strings × two conductors — so two 4-pole units
split by inverter (S1+S2, S3+S4), never two 2-pole. |
One visit answers 0, 1, 3, 4, 6, 8 and 9 — and 0 should be answered standing at the meter, not at this wall. Questions 2 and 5 are design calls they may want to come back on, and 7 is for whoever signs the install off.